JOHN’S TOP TIP
something I was used to doing for clients when I worked for a law firm. “Every day there was something new to grapple with, but I never thought there was anything we couldn’t do – there was always a solution and that’s what I really enjoyed, working through challenges.
“All the subcontractors were fantastic – there
were so many issues we had to deal with but none of them said to me, you’ve never built a house, so just let us get on with it. We were able to work out how to do things day by day.” While every self-build project presents its own ‘bumps in the road’, the constantly reoccurring challenge at The Pump House was how to approach the curved elements of the building design. To create curved walls, insulated concrete
form (ICF) – blocks that are essentially a polystyrene sandwich’ with a concrete filling – was chosen as the building structure system best suited to the task. “It’s a great system and the ICF suppliers helped a lot,” says John, “but working with ICF was a completely new experience for many of the building team.” Curved walls (and sometimes ceilings too) posed a problem when it came to fiing plasterboard internally or rendering outside. John says: “If anything needed a bend, I got involved. I pretty much learned how to bend every type of material.” He continues: “The roof decking was just one example of the challenges I got involved with. The building is crescent-shaped, so the joists had to be all different lengths. We also had an
36
www.sbhonline.co.uk
essentially flat roof so we needed to work out how to get the rises and falls of that roof to take rainfall away. Our joists weren’t running in the same direction as the falls, so we constructed two layers of decking. e laid one layer completely flat fied to the joists, and then laid out battens at whatever angles we needed fied to the flat deck. ach piece of plywood had to be cut four times because of the curves and then they had to do it twice because we had two layers.” John and his team were faced with another pule when it came to fiing plasterboard to the two-storey-high curved ceiling above the lounge-dining area: “I worked out we had to put down strips fied to the oists and then a batten fied to all of those so there were essentially rails to follow when fiing the plaster board. We also used several layers of a slightly thinner plasterboard too so they would bend more easily.” John’s ingenuity was called upon once more when it was realised that aluminium strips on the roof edge would have to be bent in plan and elevation. John designed jigs for a chop saw to cut between 100 and 200 slots in each aluminium strip so that they could be fied to the roof in the shape needed.
Glazing was yet another aspect of construction that was impacted by curves – on the southern elevation of the house, a convex curve was needed for the windows at second-storey height and then a concave curve for the smaller doors onto the patio. On this occasion at least ohn didn’t have to figure out a solution and
Be onsite at the build as often as you can and get involved in the detail of everything you can – otherwise, you can’t guarantee what you’re going to end up with. This was absolutely vital in our case because the design was so unique and outside of what our builders, carpenters and electricians would normally do. We inherited detailed drawings and had even more drawn up and worked very closely with the architects. But even with that it was hard sometimes for the builders to visualise certain parts of the construction. The builders would say to me, what’s this supposed to be like? I’d phone the architect and they’d supply a freehand sketch, then we’d give that to the builders and the next day that’s what they would build. Something like that happened almost every day during the initial construction phase.
nov/dec 2024
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60