search.noResults

search.searching

dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
HIGH POINT


“Once the roof was done and it was all watertight.”


were also key to the design process. “They do all the engineering calculations,” he explains. “They tell you if something’s possible or not, calculate the truss requirements etc.”


THE BUILD BEGINS


The first major job to be tackled on site was the services. The biggest part of this was removing a transformer pole that was on the site. “We had to liaise with Western Power to get that removed and put all the supplies underground,” Mark explains.


Although engaging suppliers to run services to an empty site can often prove to be something of a headache, Mark says in his case, “they were all great.” All the underground work and the installation of a new transformer pole was taken care of. “I can’t speak highly enough of them,” Mark remarks. “Moving a transformer is a significant task.”


Mark and Sharon benefitted from a bit of serendipity, as the existing transformer pole was in need of replacement anyway. Along with their build, two other houses were going up nearby, and the pole wasn’t “up to standard.” It was therefore logical for it to be relocated and replaced at the same time.


Their site was home to some stables which had to be dismantled and reconstructed elsewhere. Groundworks – including the relocation of the pole – started onsite in June


20 www.sbhonline.co.uk


This speed of construction is one of the reasons Mark had a preference for timber frame


2016, and by August they were ready for the construction of the timber frame.


The frame only took two weeks to erect. This speed of construction is one of the reasons they had a preference for timber frame, along with its insulation values. “Within two weeks the roof can be felted and you can start work internally,” he says.


Mark project managed the build himself – no mean feat given that he also runs his own business, but admits it is challenging: “It’s hard, because you’re totally reliant on people turning up, but it’s manageable!” He says working from home is a huge advantage however: “I’m onsite virtually the whole time. It makes a huge difference, I’m lucky.” However, should circumstances change, Mark is adamant he would still project manage. “The cost saving is significant,” he says, “but you have to be prepared that the project will probably


november/december 2018


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52