INDUSTRY ARTICLE


Figure 3: The measured data show pronounced variance over the course of the year. Measured wind speeds were highest in winter and lower in summer. Given this, performance of long- term measurements over one complete year or measurements during the transition between the seasons are important to obtain valid data of the potential yield.


This finding is also highly significant for other sites, as measurements (using methods such as laser-aided LIDAR systems) often only extend over a few months for cost reasons. However, the evaluation of the measured wind data


WILL THE WIND FARM BE PROFITABLE? The test wind mast supplies significant information on the wind conditions in the forest areas of lower mountain ranges in general. So far, there have been only a few studies on this subject in Germany.


However, in addition to these findings, the data also answer a very specific question, i.e. whether profitable operation of a wind farm is possible in the forest region of Hessenreuther Wald.


shows that measurements that are conducted only in summer or winter do not deliver reliable, representative results and may cause the potential of the site to be significantly over- or underestimated in this case.


This is the issue facing Natural Energy Solutions GmbH & Co KG, Erbendorf, the local energy initiative which plans to build a wind farm there. However, for the multi-million-euro project to be realised successfully, profitability and cost-effectiveness must be ensured.


As is often the case, this quickly led to the question of whether wind conditions and thus ultimately also the potential energy yield at the site, would be sufficient. After all, large turbines and state- of-the-art technology also mean high purchase and installation costs. However, in this context the complex topography of the low mountain region is far more important. Extensive commercial forests cover the surrounding valleys, hills and mountains, so that the relief greatly influences the air currents at the site.


8


www.windenergynetwork.co.uk


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116