Parameter
Potential Maintenance Activity
replacement Paint and repair
J-Tube and ladder cleaning
Cable
Additional cable laying within a new location
Maximum number of cables and cable lengths: (i) 550km AC interarray cables;13x10km HVAC interconnector three-core cables; 4x100km of HVDC export cables.
Cable inspection Any additional vessels required assumed to be within the worst case of 6 work boat vessels per day.
Cable burial using surface protection
Assessment includes: (i) protection required at all export offshore cable corridor crossings - 40 crossings identified (4 EAONE export cables x 10 existing/planned cables); (ii) protection required at all inter-array cable crossings - 5 crossing identified. Each crossing assumes area of 100m (50m either side of the crossing) x 6m x 1m height required. (iii) Additional scour protection assessed within East Anglia ONE site see "Additional scour protection around foundations".
Worst Case Assessed in the Environmental Statement
FurtherWorks/ Annex 1 Surveys /Action Needed
required
No further action required
No further action required
Alert the MMO - review availability of current survey data in proposed location
No further action required
Alert the MMO - review availability of current survey data if activities are outside the project envelope. For activities within the project envelope, no further action required (to be reviewed triennially)
Outline Operations and Maintenance Monitoring Plan Offshore
Page 10
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17