case study
“The architects introduced a natural stonework facade at the tower base with a ‘Cartsdyke Apartments’ engraving
system is now used to heat all flats in Cartsdyke Apartments. Clyne added: “The existing heating system was electric storage heating – very inefficient and expensive. That, coupled with old draughty windows and a failing EWI render system, made the building inefficient and expensive to heat for all. River Clyde Homes and ourselves looked at other possibilities and arrived quickly at this being the best option to install biomass. The system brings a much reduced heating bill to the tenants and a warm environment.”
Cartsdyke Apartments
Project cost: £2,061,000 Rent: £77.18 p/w (caretaker & laundry facilities inclusive) Main contractor: Morris & Spottiswood Principal designer: AHR Architects Architect: Murray: Russell Architects Interior designer: ARKA Biomass contractors: Gibson Goold Structural engineer: David R Murray and Associates Service consultant: Atelier Ten Render: AFS Windows: CMS Window Systems
Look and feel
Beyond structural improvements, RCH wanted to bring a new look and feel to the high-rise internally that would contrast with typical 1960s tower blocks. The association appointed architect Murray Russell, who claimed to have brought the ‘feel of a hotel’ to the development. The architects introduced a natural stonework facade at the tower base with a ‘Cartsdyke Apartments’ engraving. They also redesigned the lobby to include grey tiled walls, bright wooden doors and ‘premium’ design touches such as embossed mailbox numbers, steel elevator doors and secluded meeting spaces. The clever redesign also meant there was enough space to create two
additional wheelchair-accessible flats, suitable for residents with mobility problems. As requested by tenants during the consultations, level access features such as automatic sliding doors had also been incorporated in the lobby and all communal areas. The inclusion of an entrance porch and an external ramp were also welcome additions to the development, as was the resurfaced access road.
Challenges
“The main issue we faced was weather during the render works and plant room build, which delayed the removal of the scaffold and in turn held up the lower level works and the common area reconfiguration,” explained O’Rourke. Gordon Clyne seconded this in his assessment, highlighting the
building’s exposed location close to River Clyde meant stormy weather had been the contractors’ main concern, alongside the pace at which the biomass system design was realised.
“RCH got very few complaints over the course of the works, largely thanks to the association’s willingness to listen to its tenants’ requests”
Consultation is key River Clyde Homes says all the work was completed with minimum
disruption to tenants, who had been informed about imminent works in order to make any necessary arrangements. “As all the works were carried out while the tenants remained in their
homes, the common area works were challenging with people coming in and out of the building and common areas,” explained Joanna O’Rourke. “The main priority [for us] was to ensure the areas were safe and that tenants were disrupted as little as possible. The contractor also came in at night to carry out some of the floor tiling as these were low traffic times,” she added. O’Rourke noted RCH got very few complaints over the course of the
works, largely thanks to the association’s willingness to listen to its tenants’ requests. “When there’s something that people want, they are ready to put up with some disruption in order to get it,” she concluded. “I have to say the tenants were great throughout the works and were very patient and accommodating.”
26 | HMM January 2017 |
www.housingmmonline.co.uk
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52