The consequences of poor programming can be disastrous and each individual organisation will have to decide what time of year is best for the work to be carried out in context of any engineering requirements and climatic conditions


can be drawn up and, potentially, the works tendered. This will allow you to obtain current market prices for the remedial works and start to programme and plan health and safety etc. Additional costs, such as external fees, sometimes VAT and contingencies should all be planned within the budget. During the project works itself, a monthly cash flow forecast should be obtained from the successful contractor so that the client has a good angle on what funds will be required and when, and the terms on which the monies will need to be paid. This is particularly important when seeking funds from external bodies as there very often can be a delay in payment from the main funding authority to the client and, in turn, to the contractor. It is best that this is known about


Typical site before refurbishment


up front and discussed with the contractor at the time of appointment. Many contractors are happy to work with this as long as they know about it.


Project Programming


It is often surprising how long a refurbishment project can take to plan. The consequences of poor programming can be disastrous and each individual organisation will have to decide what time of year is best for the work to be carried out in context of any engineering requirements and climatic conditions.


Typically, the warmer spring, summer and autumn months are best for refurbishment work as materials and techniques employed need a kinder climate in order to be installed


successfully, and certainly be implemented. I would always advise planning a project the year before the works are to be executed, but realise that this is not always possible. Recently, we refurbished a synthetic pitch from conception and agreement to completion in four months. This was a significant project and only commissioned because we had the experience and expertise to be able to advise the client that it was feasible. This strategy, however, is not without risk and you are reliant on other factors falling into place in order to deliver success. So our advice with this is be careful and give yourself as much time as possible to plan the project.


As discussed below, there may well be additional considerations such as finances


Detail of a refurbishment plan 104 I PC OCTOBER/NOVEMBER 2015


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156