This page contains a Flash digital edition of a book.
THE EXPANSION


According to the terms of the fixed- price contract, the consortium has 1,883 days (269 weeks) to deliver the project from the commencement date, August 25, 2009. If GUPC delivers the project ahead of time, the ACP is committed to pay the consortium a bonus of $215,000 per day, up to $50m. On the other hand, the ACP will deduct $300,000 per day up to $54m (roughly six months) if GUPC incurs any delays. If the project runs late, which is neither in the ACP’s nor in the consortium’s plans, the contractor will lose the opportunity to make this money [$50m].


On both the Atlantic and Pacific side, the lock construction sites are changing by the day with trucks roaming and huge cranes sitting at the bottom of the future locks’ chambers. The gigantic cranes at peak season [mid 2012] will multiply to 27 cranes on each site with the task of being the conductors for placing concrete at the same time in the three chambers.


In October 2010, a team comprising ACP and GUPC representatives travelled to Lyon, France, to visit the Compagnie Nationale du Rhône, which has built and tested a model of the locks’ hydraulic systems. ‘The results were excellent and the designer has incorporated the improvements in the lock design,’ says Aleman.


The expansion programme still has a few minor contracts to call to tender in the coming months to complete its suit of contracts.


That includes calling a tender for new submersible hydraulic cylinders for Gatun Locks upper level gates and Pedro Miguel Lock gates. These will replace the present cylinders, which were not built for submerged operation


A 1.8km long backfilled cellular cofferdam water barrier will create the farthest part of the access channel’s eastern bank and separate Miraflores Lake from the new channel.


and will be subject to this condition when the level of Gatun Lake is raised by 45cm. ‘There will be other small contracts to be tendered, but that of the hydraulic cylinders’ is the most important to come,’ says Quijano. To support the raising of the level of Gatun Lake there is other work that needs to be accomplished in the present locks, such as the sealing of the upper hinging mechanism and the gates upper skirt that supports the walkways. Two taller maintenance caissons for the Gatun spillway were fabricated in Canada to accommodate the higher lake operating level.


These are required to perform maintenance in the dry to the taller gate bodies once they are all modified to operate at 45cm higher Gatun Lake. The extension of the spillway gates will be done mostly in-house, by the ACP’s industrial facilty, explains Quijano. Because of the new elevation of Gatun Lake, the spillway will operate 45cm


above its present level of 26.7mtr. Gatun Lake will be at fullest level of 27.1mtr by the end of 2014.


GUPC is required to excavate around 40m cu mtr for the construction of the Atlantic and Pacific locks, almost as much as the total dry excavations of nearly 47m cu mtr needed for the Pacific access channel. The ACP has awarded four dry excavations contracts totalling $371m to dig the approach to the future Pacific lock complex. The first three were awarded to Constructora Urbana, CUSA (PAC 1), the Mexican-Panamanian Cilsa Minera (PAC 2) and Costa Rica’s Meco (PAC 3). The first three of four dry excavations contracts have been completed.


The final and largest dry excavation contract (PAC 4), was awarded to the Mexican, Spanish and Costa Rican joint venture ICA- FCC-MECO. The $267m PAC 4 is the second-largest and most complex project after the new locks – representing a key portion of the expansion’s new access channel linking the new Pacific locks with Gaillard Cut, the narrowest stretch of the Panama Canal. This contract calls for the installation of a 1.8km long backfilled cellular cofferdam water barrier, which along with the 2.3km Borinquen dam, will create the farthest part of the access channel’s eastern bank and separate Miraflores Lake from the new channel.


PAC 4 had been slow in starting, thus falling slightly behind the base programme, but has made tremendous progress and is now at 44% of its execution, achieving record excavation production and completing the cofferdam,‘ says Quijano. The consortium in charge of PAC 4 has already excavated 10m cu mtr and [its] companies had been very efficient,


Cofferdam water barrier


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112