This page contains a Flash digital edition of a book.
Existing measures, with projected energy savings made


Photovoltaic (PV) or solar generation Solar water heating


Installation of variable speed drives on selected pumps


Lighting level review and reduction


Staff engagement – estimated outcome Totals


Electricity savings estimate (kWh/yr)


10,000 2,900 1,000 11,800


4,500 27,300


10,000 12,900


estimate (kWh/yr)


savings


Gas


(te CO2/yr)


5 1


1


Carbon dioxide saving


saving (£/yr)


1,000 80


100


Cost


Guide price (£)


27,500 5,000


250


6 1,060 3,500 4


17


3,600 5,840


Simple payback


period (yrs)


27.5 62.5


2.5


1,000 37,250


Figure 1: Measures in operation, with projected energy savings made, projected payback periods and expected savings to be made


Recommended further measures, with estimated energy and cost savings


Installation of ground source heat pump


Voltage optimisation


electricity savings (kWh/yr)


Guide


electricity savings (kWh/yr)


–33,000 176,000 9,000 Gas


Carbon dioxide savings


(te CO2/yr)


saving (£/yr)


Cost


Guide price (£)


Simple payback period (yrs)


14.8 1,900 50,000 26 4.8 900 9,000


Figure 2: Recommended further initiatives. The figures shown are estimates of what savings could be made through the adoption of these measures


Metered energy Actual


Electricity kWh/sq m Non-electricity kWh/sq m


Carbon kg CO2 emissions/sq m Building total Kg CO2 Building total cost (£)


75


184 74


180,511 31,626


Benchmarks


Adjusted Good practice 79


184 76


185,729 32,597


55


385 101


244,746 41,414


Typical 80


540 143


347,007 58,782


Figure 3: Comparison of electricity use and carbon emissions with benchmarks >


an energy management consultancy, to conduct an assessment of the impact of these improvement measures on the energy efficiency and carbon footprint of the Wembley site. The commission was the result of CIBSE’s ongoing programme of investigations into real-life building performance. The detailed analyses of the overall energy use and performance of heating, ventilation and other systems were undertaken using the CIBSE TM22 procedure. The energy saving measures taken as a result of the refurbishment have been shown to have produced substantial projected savings – see Figure 1, above. These measures were the installation of photovoltaics and solar-powered water heating. In addition, a staff- engagement programme was introduced to help improve energy management, which produced notable estimated savings. Together, these three changes have produced


assessed annual cost savings of nearly £6,000, within a range of identifiable payback periods (Figure 1). Power Efficiency also recommended a range of further


energy saving measures that could be undertaken at the site. These were the installation of a ground-source heat pump and the application of voltage optimisation. Projected savings are shown in Figure 2. Below, we look in more detail at the impact of the


36 CIBSE Journal February 2011 10


3.3 0.3


refurbishment measures taken at the site. We also explain our recommendations for further improvement. But first, let’s look at the metering arrangements.


Energy consumption Metering arrangements at the site comprise one non- half-hourly meter for imported electricity and one meter for gas used on site. In addition there are four non-half-hourly sub-meters dedicated to metering the Life Building, the main boiler plant and appliance bay space heaters, and associated gas consumption. A single non-half-hour meter logs the imported consumption from the PV installation. Fiscal metering data is uploaded to the supplier’s web portal and can be interrogated remotely by the LFB. Energy generated on site by the PV system has


reduced the amount of imported electricity. Electrical energy generated by the PV system since installation in 2008 was, at the time of the study, 20,900 kWh, therefore averaging in the order of 10,000 kWh per year, representing a contribution to the electrical income of 6.2%. The total electricity consumption for 2008 was


194,728 kWh plus the estimated 10,000 kWh, which resulted in a combined total of 204,728 kWh, whereas the total electricity consumption for 2009 was 180,968 kWh plus the estimated 10,000 kWh, thereby resulting in a combined total of 190,968 kWh. The above totals indicate an overall reduction in the sites’ total electrical consumption of 13,760 kWh (6.7%). Gas is consumed on site by five gas-fired boilers, two


space heaters, and the kitchen appliances. The total gas consumption for 2008 was 477,182 kWh. In 2009 it dropped to 446,067 kWh, a fall of 6.5%. A comparison of the metered energy use at the site


with ‘Good Practice’ and ‘Typical’ benchmarks is shown left (Figure 3).


Existing improvements Photovoltaics: The fire station has a photovoltaic (PV) system which generates 11.3 kW of renewable electricity, and has a predicted average annual output of 10,000kWh. This represents an annual emissions saving of 5 tonnes and an annual cost saving of £1,000, increasing to nearly £5,000 with the benefit of electricity feed-in tariffs. These figures are based on an electricity charge of 10p per kWh. Half the cost of the system was covered by an Energy


Efficiency Loan, leaving the LFB with a bill of £27,500. This produces a payback period of 27.5 years, but this timescale has been reduced considerably as a result of the introduction of feed-in tariffs in April 2010. Solar heating: The site has a solar-powered water-


heating system, using evacuated tube collectors covering an area of 5 sq m on the roof of the Life Building. The system has not been monitored, but it is capable of cutting annual gas consumption by 2,900 kWh, saving an estimated £80 a year. This would also reduce CO2 emissions by 0.5 tonnes a year. With these cost savings, the payback period for the system is estimated at 36


www.cibsejournal.com


>


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72