WAREHOUSING/FACTORIES


U


nlike the 2018 MLCC shortage and 2021 chip shortage, today’s supply chain pressures are being driven by a structural change in demand, with the enormous growth of AI computing putting pressure on production capacity.


Selina Lee, explains how a proactive approach to supply chain management can help reduce purchase price variance (PPV) and protect production timelines.


STEP ONE: LOOKING BEYOND THE IMMEDIATE PURCHASE PRICE PPV refers to the difference between the previous purchase price and the new price actually paid for a component or material. When component prices are moving quickly, reacting only when an increase reaches the bill of materials can leave manufacturers with limited options. Ryder’s approach begins with monitoring


raw material markets, including metals, IC manufacturers and the raw materials used in PCB production. Where supply is expected to tighten, working with customers to forecast demand and advance purchasing can allow suppliers to secure raw materials and allocations before demand increases further. This cannot eliminate market-driven price


increases, but it can buffer inventories at earlier pricing levels and reduce the immediate impact on the bill of materials. In fact, Deloitte’s 2026 analysis of AI infrastructure notes that companies that had locked in component supplies months in advance may face less immediate pressure, with procurement potentially shifting from just-in-time to just-in- case as supply constraints persist.


STEP TWO: BUILDING RESILIENCE THROUGH MULTIPLE SOURCES A supply chain that depends too heavily on a single component source can be particularly vulnerable when availability changes. For electronic components, Ryder industries


is, therefore, qualifying suppliers across China, Southeast Asia, Europe and North America, with particular focus on high-volume components such as ICs and multilayer ceramic capacitors (MLCCs). Having multiple qualified sources can create


greater flexibility when a supplier becomes constrained, while also providing greater visibility of pricing and availability. This approach reflects a wider move towards


supply-chain diversification. DHL reports that 57 per cent of companies with China- based production have adopted a ‘Supplier +1’ strategy, retaining their existing supplier while adding at least one additional source in another region. The approach is designed to reduce reliance on a single supplier and provide an alternative when disruption affects one part of the supply chain. For an EMS provider, however, qualifying an


alternative supplier is not simply a purchasing decision. Their components must additionally be verified to meet the required technical, quality and reliability specifications.


HOW ELECTRONICS MANUFACTURERS CAN REDUCE THE IMPACT OF SUPPLY CHAIN DISRUPTION


By Selina Lee, VP of SCM, Ryder Industries


Copper-clad laminate (CCL) manufacturers are into their seventh round of price increases this year, while DRAM contract prices increased by 60 per cent quarter-on-quarter in Q2 and lead times for microcontrollers have extended to as much as 52 weeks


STEP THREE: USING ENGINEERING TO REDUCE COST When component prices increase, changing suppliers is not always the only option. Engineering can also be used to identify where costs can be removed from the product itself. Ryder works with suppliers and customers


on Value Analysis and Value Engineering (VAVE), examining material specifications, manufacturing processes and design choices to identify opportunities to reduce cost without compromising performance or quality. Ryder’s current program is examining


current work including metal stampings, transformers and adapters, while similar VAVE exercises can be carried out with customers to identify savings, from design through to production. This makes cost reduction less dependent on negotiating a lower unit price. Instead, the aim is to understand what is driving the cost of a component and whether the same function can be achieved through a different material, process or design.


24 OCTOBER 2026 | FACTORY&HANDLINGSOLUTIONS


STEP FOUR: QUALIFYING ALTERNATIVE COMPONENTS There are also situations where the problem is not price but availability. If a specified component becomes


unobtainable or commercially impractical, an alternative may need to be identified and qualified. For an EMS provider, this can include electronic components as well as PCB substrates. The process needs to go beyond finding a part with a similar specification. Engineers need to establish whether the alternative meets the required electrical, mechanical and reliability requirements before it can be introduced into production. Ryder works with customers through the


evaluation, testing and approval process, providing a route to alternative components while maintaining the required quality and compliance requirements. This becomes particularly important when


a component is critical to production. Finding an alternative after a line has already stopped


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46