Coal-to-gas conversion |
Engineering a gas-fired future for Spain’s Aboño 2
Plant life extension, emissions reduction and cleaner, more flexible generation – just some of the key benefits of a coal-to-gas conversion carried out at EDP’s Aboño 2 power plant in Spain
John Goldring Managing Director, RJM International
The Aboño power plant, unit 2 to the left (Photo: EDP)
12 key project phases
1 Fact-finding (baseline performance test, site survey and combustion audit)
2 CFD modelling programme
3 Engineering design phase and first draft of O&M manual
4 Procurement and manufacture of new hardware
5 Installation, carried out by EDP’s main contractor, Duro Felguera, under Wood and RJM supervision
6 BMS and DCS upgrade 7 Commissioning 8 Optimisation 9 Performance guarantee tests
10 Training of plant personnel on new operational procedures.
11 Final O&M manual issued 12 Project completed
The Aboño 2 plant was commissioned in September 1985 and consists of a 556 MWe opposed wall-fired Foster Wheeler boiler with 36 burners in a six column/three row configuration. As well as coal, the plant fired additional fuels including fuel oil, as well as blast furnace gas (BFG) from an adjacent Arcelor-Mittal steelworks. Located at Gijón in Spain, Aboño 2 is owned and operated by EDP (Energias de Portugal), a major global utility generator with operations in Europe, the Americas and Asia-Pacific. EDP has a total installed capacity of over 32 000 MW and is committed to clean energy. It drives global growth through electrification, focusing on renewables, resilient networks, and balanced investment for a sustainable future.
Project objective – reconfiguring the plant to fire natural gas As part of Spain’s national plan to decarbonise the economy, legislation was introduced to cease all coal-firing by the end of August 2025. This meant that coal-fired power plants either had to shut down or transition to an alternative fuel. In this case, EDP set aside an investment budget of mid-double-digit million euros and selected Wood (engineering consultancy and boiler OEM, via its acquisition of Amec Foster Wheeler) to undertake a project scope to explore what the plant’s options were for continued generation. Duro Felguera was selected as main EPC contractor.
Wood carried out a number of detailed feasibility studies to evaluate alternative pathways
NOx NOx
for modifying the plant and proposed to EDP a set of engineering designs, based on economic viability, environmental impact and operational efficiency.
Project procedure
Once it was determined that a conversion from coal to natural gas would be the most viable way forward, Wood appointed RJM International to tackle the combustion part of the project. This followed a complex tendering process and submissions by a number of multi-national burner technology companies. RJM’s scope included the design and manufacture of the new burner system that would be needed to meet project objectives, in
terms of significantly reduced emissions, more reliable operation and continued fuel flexibility. It was also important to retain the capability to fire blast furnace gas from the steelworks, as this enabled efficient use of a waste fuel contributing to green steel manufacture, as well as reducing Aboño’s own consumption of natural gas. An additional requirement was that the plant should be future-proofed with the in-built capability for the burners to fire hydrogen, thus ensuring that a “next generation” level of plant life extension in a zero carbon environment could be achieved. At the start of the project, Wood and RJM conducted a site survey, a baseline unit performance test, a full combustion assessment, a boiler part pressure test and an economiser
Left: CFD image showing NOx
before (coal) and after (gas). (Image: RJM International)
Above: CFD gas burner image showing compact flame profiles. (Image: RJM International)
38 | November/December 2025|
www.modernpowersystems.com
levels
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53