| Transmission & distribution UK–German link progresses
NeuConnect, the planned HVDC link between Germany and the UK – two of Europe’s largest energy markets – continues to progress, with start of construction expected later this year, and operation targeted for March 2028
Following “significant market interest in NeuConnect’s procurement programme”, cabling and converter contracts for the 1.4 GW, ±525 kV, HVDC link – totalling over 1.5 billion
euros – have been awarded as follows: ● Cabling works: the contract to design, manufacture, install, test and commission the 725 km interconnector (one of the world’s longest) was awarded to Prysmian Group.
● Converter stations: the contract to design and build two converter stations, one in the UK and the other in Germany, was awarded to Siemens Energy. The link will employ HVDC Plus technology, with the ability to perform a variety of additional grid support functions, including regulating AC voltage and stabilising a weakened AC grid.
In addition, NeuConnect has appointed a joint venture of Arup and Fichtner to provide: project and commercial management; safety, health, environment and quality (SHEQ) management; and consenting oversight across both the onshore and offshore elements of the project. Led by Meridiam, Allianz Capital Partners and Kansai Electric Power, NeuConnect is a privately-financed interconnector. Early-stage development input on the project was provided by Frontier Power and Greenage Power. The cable route runs between the UK converter station located at Grain, Kent, passing through UK, Dutch and German waters, to a landing point at Fedderwarden, Lower Saxony, to connect with the German converter station, near Wilhelmshaven.
The link will employ a pair of mass- impregnated (MI) paper insulated copper cored DC cables (to be manufactured at Prysmian’s Arco Felice factory near Naples), with fibre optics in some sections for control, monitoring and communication.
Prysmian plans to deploy three of its cable laying vessels: Leonardo da Vinci, Cable Enterprise, and Ulisse.
Last year, UK prime minister Boris Johnson and former German chancellor Angela Merkel confirmed their support for the NeuConnect project, with the new UK–German energy link seen as delivering a wide range of benefits
including: ● Greater energy resilience and security of supply. NeuConnect will allow electricity to flow in either direction between the UK and Germany, helping to deliver a more secure and resilient energy supply, and with increased competition in each market also helping to deliver significant consumer benefits, the developers say, as well as providing a new market for excess German renewables.
● A significant reduction in carbon dioxide, UK interconnectors Norway
Moyle 500MW
Denmark
Rep. of Ire and
Irelandl EWIC 300MW UK UK
Greenlink 500MW
Aquind 2000MW
Existing links Under construction
Under development
Under development
Notes: Aquind consent refused, being appealed. NorthConnect on hold. FAB Link being rescheduled, FID targetted for 2025. ElecLink at commissioning stage. Nautilus and Eurolink are proposed ‘multipurpose interconnectors’, connecting to wind farms en route. One of IFA’s two 1000 MW bipoles was damaged by Sept 2021 fire at UK end, return to full capacity expected Dec 2022
by “integrating renewable energy sources in the UK and Germany.” Detailed analysis commissioned by NeuConnect is said to show that the project will deliver a net reduction in carbon dioxide emissions of 16 MtCO2
over 25 years.
● Development of what would be the single largest Anglo-German investment project and creation of an “important symbolic link” between the two economies.
NeuConnect has also been highlighted by the UK government’s investment minister as a key project to support the UK’s Net Zero goals, while in Germany the government has included NeuConnect in its long-term energy development plan.
The project is one of several interconnectors developed under Ofgem’s cap and floor regime in the UK, which has proved successful in achieving its stated aim of “unlocking investment in electricity interconnectors”, by providing developers with an appropriate balance of risk vs rewards. The floor is the minimum amount of revenue that an electricity interconnector can earn. If an interconnector does not receive enough revenue it will be ‘topped up’ to the floor level by the system operator using funds derived from transmission charges applied to all users of the national transmission system. The cap is the maximum
amount of revenue from the interconnector. Excess revenue, above the cap, is transferred to the system operator, which will in turn reduce transmission charges.
For NeuConnect, as a new entrant to the energy market and one of the very first UK interconnectors to be delivered using project finance, it was necessary for variations to made to Ofgem’s existing cap and floor regulations. In May 2020 Ofgem approved such changes, enabling the delivery of project-financed schemes such as NeuConnect. NeuConnect was granted Project of Common Interest (PCI) status by the European Commission in 2019 (enabling it to benefit from accelerated permitting procedures and funding). As with a number of other UK projects, NeuConnect’s PCI status lapsed with the UK’s exit from the EU. However, the UK and EU are expected to introduce a new category, ‘Projects of Mutual Interest’, for UK-EU projects, and NeuConnect, which enjoys strong German and UK support, as already noted, may be eligible. Interestingly, the UK part of NeuConnect does not require a Development Consent Order (essentially planning permission) from central government. Onshore planning permissions have been awarded at a local level (by Medway Council) and offshore permissions awarded by the Crown Estate and other relevant bodies.
www.modernpowersystems.com | May 2022 | 25
FAB Link 1400MW
IFA2 1000MW
ElecLink 1000MW
Nemo Link
1000MW
GridLink 1400MW
France France Belgium Belgium Luxembourg Germany
Nautilus 1400MW
IFA 2000MW
Eurolink 1400MW
BritNed 1000MW
NeuConnect 1400MW
Denmark
Netherlands
NorthConnect 1400MW
Viking Link 1400MW
NSL 1400MW
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45