| Refurbishment
Expert team powers turbine overhaul
Collaboration, experience and expertise were at the heart of the Unit 1 turbine generator overhaul at Maentwrog hydroelectric power station in North Wales
Above: Turbine case and guide vane assembly ready to receive runner
Above: Following completion of disassembly, all parts were organised and ready for refit
THE TEAM AT GREEN HIGHLAND RENEWABLES (GHR), experienced turbine engineers, were thrilled to be selected by Quartzelec, an independent electrical engineering group, to work on the Unit 1 turbine at the Maentwrog Hydroelectric Power Station in North Wales. Operated and managed by Nuclear Restoration Services (NRS), a subsidiary of the Nuclear Decommissioning Authority, this project allowed GHR to apply its specialized skills to a critical component of this historic hydroelectric facility.
Strip-down The strip-down of Unit 1 took eight days. The work began
with a fingerprint test carried out at different machine loads, including temperature and vibration checks. During the turbine strip-down, all parts, including the surface conditions, were visually checked. Any signs of wear or damage were documented, and, where needed, the parts were sized up for repair. This detailed data gathering is vital in enabling ongoing cross-referencing of previous and future maintenance work, helping prevent unplanned outages in the future and ensuring maximum performance. The team knew that the generator had an overhung shaft, which meant the turbine and runner assembly had to be stripped down, to unthread the rotor Two locking elements secured the runner onto the shaft, which was then drawn off with a mandrel and jacking assembly. The turbine was then stripped down to its bare spiral casing. Before stripping down, both the lower and upper chamber alignments were checked. These were reviewed, and the results influenced the rotor position and then the runner-to-casing alignment. During the strip down all guide vanes were dismantled and removed. The guide vanes and the runner were non-destructive tested by a dye penetrant. A specialist sub-contractor was brought in by Quartzelec to carry out this work. This method highlights any cracks in a structure, joint or weld. All relevant parts were sized using a range of precise
Above: Turbine case with guide vanes in situ
and calibrated measuring equipment to ensure that all the clearances were correct.
Reassembly
Once everything had been maintained, measured, and documented, the team rebuilt unit 1 turbine, which took another eight days. During the turbine rebuild, the runner radial and angular alignments were carried out and documented. The guide vanes were refitted, and the end float and squeeze were measured. Prior to fitting the runner, a full movement check was also carried out to ensure the correct operation seal when in the closed position. Following all of this work, the spiral casing was pressurised to ensure all sealing faces were correct. Based on assessments made during the disassembly
the team made several recommendations, including adjusting the shimming of the bearings to better align the rotating assembly to the turbine casing, which were all applied. NRS operated the machine for GHR to conduct a
recommissioning fingerprint test of the turbine. The results were then compared to the initial test results to ensure optimum performance. The tests also showed lower vibration in the drive end bearing than what was first recorded in the initial test.
Collaboration The team worked closely with NRS and Quartzelec and
were delighted to be able to welcome two of NRS’s apprentices to the project to learn more about this fantastic source of clean power. Members of the Voith Hydro team were on-site and
vital to the process. The team worked closely to help verify measurements and findings during disassembly and rebuilding. Given their experience working on these types of power stations around the world, they were able to provide their world-leading expertise and resources throughout the whole process. Following the full ten-year maintenance overhaul of unit 1 Turbine, it has consistently delivered clean electricity since September 2024.
Above: Runner mandrel being installed
Above: Runner nose cone going to final torque using hydraulic equipment
Above: Draft tube being lifted back into place
Above: Rotor shaft diameter being measured
www.waterpowermagazine.com | December 2024 | 35
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45