Dams |


Diversion begins for Polihali dam


The Lesotho Highlands Development Authority, consultants and contractors marked a major milestone in the Polihali Dam construction programme in early August 2023 by closing the flow of the Senqu River to start the diversion of its waters through the project’s diversion tunnels


From top to bottom:


Dumping of materials to close the river flow


Clearing access for the diverted water enter the diversion tunnel


Tente Tente, LHDA’s CE, witnessing first waters to exit the diversion tunnel


THE LESOTHO HIGHLANDS DEVELOPMENT Authority (LHDA), consultants and contractors on the Polihali Dam marked an early construction milestone on 4 August 2023: the diversion of the Senqu River by the pre-cofferdam, and the subsequent diversion of the river into and through the diversion tunnels ahead of the construction of the cofferdam upstream of the Polihali Dam wall. Speaking on site, Tente Tente, CE of the LHDA,


said: “This is quite an achievement to the engineering fraternity. It is a key moment of the construction programme because unless this happens, no other elements of dam construction can happen. It had to happen now because the timing of it during the winter season without rain was critical. If you miss it by a week or two, you may miss the entire window by another twelve months. We are proud of everyone who has had a hand in this work. It is indicative that Phase II, just a couple of months after being officially opened by our principals, is indeed now going full steam ahead. Our consultants and contractors have hit the ground running, and we are all excited for what this means for the project, and for Lesotho and South Africa.”


Excavation work The main dam – Polihali Dam – requires extensive


excavation of the foundations before work begins in bringing it up in height. The works in the foundations require dry access to enable the rock to be excavated down to sound rock, to allow grouting of the rock to be undertaken where required beneath the dam and to allow the construction of a plinth beam which will form the water-tight seat for the upstream impermeable, concrete facing of the main dam wall. To provide this dry environment, a cofferdam is to be built upstream of the main dam to protect the main dam works from floods until the main dam concrete face is high enough to be free of such floods. In turn, to allow the coffer dam to be built there is a pre- cofferdam upstream of the cofferdam. This has the task of diverting the river through the diversion tunnels and thus around the cofferdam and the main dam foundations. Chris Hall, Project Manager of the Matla a Metsi


Joint Venture which designed the Polihali Dam and is overseeing dam construction, explained what will happen after the closure of the pre-coffer dam: “Now the Senqu River level will rise and the water will then enter the diversion tunnels to bypass the dam construction site. Whilst the riverbed is drained of water the coffer dam foundations will be excavated within the river and the flanks of the valley. The plan is


42 | September 2023 | www.waterpowermagazine.com


to complete the cofferdam before the end of October this year, according to the current master programme, and then to start on the main dam in earnest.” The diversion tunnels were constructed as part of the advance infrastructure contracts. Construction of the Polihali Dam commenced in November 2022 with the awarding of the M7.68 billion construction contract to the SUN Joint Venture. The joint venture includes main partners: Sinohydro Bureau 8 (China); Sinohydro Bureau 14 (China); Unik Civil Engineering (South Africa) and Nthane Brothers (Lesotho). Subcontractors include Melki Civils and Plant Hire (South Africa); MECSA Construction (South Africa); SIGMA Construction (Lesotho) and Kunming Engineering (China). The Polihali Dam is a concrete-faced rockfill dam,


like the majestic Mohale Dam which was constructed in Phase I of the LHWP. It will create a reservoir on the Senqu and Khubelu rivers with a surface area of 5 053 hectares. The infrastructure also includes a spillway, an intake tower and bottom outlet works, a compensation outlet structure, bridges, roads and a mini-hydropower station. The Polihali Dam adds 2 325 million cubic metres


in storage capacity to the LHWP and will increase the current annual supply rate capacity from 780 million cubic metres to 1 270, contributing towards meeting South Africa’s increasing water needs. The additional flow of water from Polihali will simultaneously increase power generation within Lesotho towards meeting Lesotho’s domestic needs and reducing the country’s dependence on electricity imports. Phase II of the Lesotho Highlands Water Project builds on the successful completion of Phase I in 2003. The major works of Phase I included the construction of the Katse Dam, the transfer and delivery tunnels, Matsoku Weir, ‘Muela Hydropower Plant and the Mohale Dam. The Phase II water transfer component comprises a dam at Polihali and a gravity tunnel that will connect the reservoir at Polihali with the Katse reservoir. The further feasibility studies for the hydropower component of Phase II have concluded that conventional hydropower is the more feasible option to meet Lesotho’s energy needs. Three potential sites were identified: two on the Senqu River and a third site at Oxbow on the Malibamatšo River. Lesotho has confirmed the Oxbow site as the preferred site for the Phase II hydropower investment. The Lesotho Highlands Development Authority


(LHDA) is the implementing and management authority of the Lesotho Highlands Water Project, on behalf of the government of Lesotho.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53