RING CRANES Ӏ JOB SITE REPORT
RING CRANE METHEDOLOGY SEES MAMMOET-GIANT OPTIMISE WIND TURBINE JACKET MARSHALLING SCHEDULE AT PORT IN TAIWAN
In Taiwan offshore wind farm specialist Ørsted Taiwan, the Taiwanese division of Danish multi-national energy company Ørsted, commissioned Mammoet Giant, a joint venture between Netherlands-headquartered heavy lift and transport specialist Mammoet and Taiwanese company Giant Heavy Machinery Services Corp., to marshal 66 wind turbine jackets for the 920 MW Greater Changhua 2b and 4a wind farms at the port of Taichung, Taiwan. RoRo is often the preferred method for moving large and heavy
offshore wind foundations onto and from vessels at port. In this instance, however, Mammoet opted to use its 5,000 tonne capacity SK350 ring crane for the job instead. A key reason behind this is that effective use of the RoRo method is condition dependent – particularly with regards to tides and weather. “We considered both RoRo and ring crane options but eventually came to them with a very clean solution of using our 5,000t capacity SK350 ring crane,” explains Joey Yu, manager of operations at Mammoet Taiwan. “This was because the port is quite famous for big tides – sometimes up to six metres in difference. For a RoRo operation, if the tide is not up to a certain level and the weather conditions are poor, it would take much longer to offl oad the jackets. What we proposed was a solution that wasn’t dependent on those factors.”
The 80-metre tall, 2,400-tonne jackets arrived on a deck carrier in batches of four. They were hoisted from the deck using the SK350 and placed onto concrete supports on the quay. The SK350’s centralised ballast weight meant that the entire ring
track didn’t need to be constructed on the quay – only the section needed to make the 130-degree slew from vessel to landing support – thus saving mobilisation time and working space. Next, with the three legs of the jacket elevated on supports, 32 axle lines of SPMT drove underneath each foundation and lifted it in tandem, using their on-board stroke. 96 axle lines of SPMT were used in total across the project. The jackets were driven to a temporary storage area in the port and placed on steel foundations resting on load-bearing mats made from sustainable bamboo. The steps were reversed for the fi nal load-out phase – the jackets
were driven back to the quayside and then lifted by the SK350 onto a deck carrier, which ferried them to the offshore installation vessel in batches of four. The effi ciency of this approach helped to minimise the uptime of high-value assets at sea, says Mammoet.
A video of the job can be seen here:
https://shorturl.at/NUQrj
42 CRANES TODAY
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55