BTS MEETING/NORTH BRISTOL RELIEF SEWER | TECHNICAL
Left, figure 11: Depressurisation System
Left, figure 12: Bespoke Temporary Works for MH01 and MH12
possible and situated key construction elements such as the TBM drive site and the two intermediate shafts as far away from residential properties as possible.
● Had a close working relationship with the emergency services including the Hazardous Area Response Team (HART) and the Urban Search And Rescue team (USAR) and allowed them to use areas of the site to undertake various mock exercises.
● Engaged in various STEM activities in both the local schools and University of Bristol
LESSONS LEARNED During the design and construction of this challenging project, many lessons were learnt that Murphy will take forward into future tunnelling projects. Below are the five key lessons learned:
Below, figure 13: MH09 and MH10 Shafts During Construction
November 2023
| 25
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49