TECHNICAL | MECHANISED TUNNELLING/HS2
Above:
Chiltern Tunnel looking south towards London
“We’re in chalk and these are naturally occurring
phenomenon across the Chiltern Hills, so it’s not unusual to have indentations,” says Clapp. Jacques adds that the tunnelling operations activated
existing dissolution features; it did not create them. Looking at the TBMs’ output and the material in the
slurry treatment plant, Align and HS2 developed a ground movement risk assessment that was carried out each day, and it helped to remove any surprises. “The accuracy of that enabled us to identify each of
those movement locations prior to anybody else, so we were out on site and in two cases witnessed the ground movements starting,” says Clapp. Tunnelling through flint was abrasive on the
cutterhead, but working in a SPZ 1 also presented challenges for maintenance, whether planned otherwise. Safe areas for tool changes were established around each of the shaft locations but outside those areas it had to be assessed whether water could be kept out of the head for long enough to carry out the work. “There were some locations where, ideally, we could
have changed tools sooner, but the machines were being well looked after and they delivered what they needed to,” says Clapp. The C1 contract brought many new aspects to
tunnelling in the UK – a variable density TBM, continuous boring, the TBM technology, and, the length of the Chiltern Tunnel to name a few, so there is a lot to learn from this project. Jacques believes the TBM innovations will become established on future projects.
14 | July 2024
“We are the first site on HS2 to have an IPT, constantly
sharing with the HS2 tunnelling working group. Through this group, our legacy will be not just to HS2, but to the wider industry,” he says. For Clapp, one of the legacies will be the apprentices
and graduates employed who are now skilled in their disciplines. “We’ve seen people who started with us with no
construction experience, leaving as fully competent and experienced individuals to join projects elsewhere. That’s a really positive legacy,” says Clapp. Jacques adds that many operatives now have
enhanced skills through using the robots on the TBMs, and new skills and expertise gained from the automatic slurry process. Align still has plenty of work to do, including
completing the 38 cross passages and five adits, which are currently 75% complete, and fitting-out the five shafts, but the team and HS2 are still taking time to acknowledge what Clapp describes as a “fantastic milestone” in completing tunnel boring. The two 16.1km-long drives were challenging but,
completing them “safely and on plan”, was a great achievement. “The result speaks for itself – and that’s not by
luck. It’s come from hard work and team effort, and we all have massive pride in that achievement,” says Clapp. “The scale of what we have here is unusual and the
challenges we’ve overcome are unusual so why would you not be proud?”
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100 |
Page 101 |
Page 102 |
Page 103 |
Page 104 |
Page 105 |
Page 106 |
Page 107 |
Page 108 |
Page 109 |
Page 110 |
Page 111 |
Page 112 |
Page 113 |
Page 114 |
Page 115 |
Page 116 |
Page 117 |
Page 118 |
Page 119 |
Page 120 |
Page 121 |
Page 122 |
Page 123 |
Page 124 |
Page 125 |
Page 126 |
Page 127 |
Page 128 |
Page 129 |
Page 130 |
Page 131 |
Page 132 |
Page 133 |
Page 134 |
Page 135 |
Page 136 |
Page 137