STOCKHOLM BYPASS | PROJECT
Control parameter
Table 3: Control programme and observational values for the temporary rock support behaviour Limit value
Visual observation of cracks in the shotcrete installed at the tunnel front
Observational Limit = No cracks appear; Alarm Limit 1 = 3m; Alarm Limit 2 = 6m
Comment
The Observational Limit is based on the design assumption that no cracks are expected in the installed shotcrete under stable conditions.
For Alarm Limit 1, the level of deformation implies that relatively large cracks have started to occur in the shotcrete.
Alarm Limit 2 is set to account for the continuously growing cracks in the shotcrete. This may indicate creeping behaviour and unstable conditions during the excavation.
Visual observation in the tunnel
Identification of cracks in the shotcrete/ Mapping
from the tunnel front. In case the observational or alarm limits stated below are exceeded, additional mapping must be performed
Inclinometer measurement in the transition part of the fault zone
Observational Limit = 7mm; Alarm Limit 1 = 12mm; Alarm Limit 2 = 17mm
The Observational Limit is based on the assumption that 30% of the total deformations has occurred when the inclinometer is installed. Inclination changes are converted to deformations.
If Alarm Limit 1 is reached, the yield strength of the pipe umbrella support is considered to be exceeded.
If Alarm Limit 2 is reached, a plastic hinge is assumed to be formed in the pipe umbrella support.
Inclinometer measurement in the centre part of the fault zone
Observational Limit = 20mm; Alarm Limit 1 = 30mm; Alarm Limit 2 = 40mm
The Observational Limit is based on the assumption that 30% of the total deformations has occurred when the inclinometer is installed and approximately 5% of the deformations occurs 10m in front of the tunnel front. Inclination changes are converted to deformations.
A plastic hinge formation is observed in the calculations when the observational limit is reached.
Alarm Limit 1 and Alarm Limit 2 are set after the value for the convergence measurement limit.
Deformation measurement and extensometer
Observational Limit = 10mm; Alarm Limit 1 = 15mm; Alarm Limit 2 = 20mm
The Observational Limit is based on a stress level in the pipe umbrella support equal to the 70% of the yield strength (characteristic value).
If Alarm Limit 1 is reached, the yield strength of the pipe umbrella support is considered to be exceeded at some extent.
If Alarm Limit 2 is reached, a plastic hinge is assumed to be formed in the pipe umbrella support.
Convergence measurement in the transition part of the fault zone
Observational Limit = 5mm; Alarm Limit 1 = 10mm; Alarm Limit 2 = 15mm
that approximately 50% of the total calculated deformation has occurred when the measurement point is installed (6m from the tunnel front).
If Alarm Limit 1 is reached, there is a risk for cracks in the shotcrete.
Alarm Limit 2 is set at a level which may indicate that the rock mass behaviour differs from the estimated variation in the performed assessment.
Convergence measurement in the centre part of the fault zone
Observational Limit = 20mm; Alarm Limit 1 = 30mm; Alarm Limit 2 = 40mm
The Observational Limit is based on the assumption that approximately 50% of the total calculated deformation has occurred when the measurement point is installed (6m from the tunnel front).
If Alarm Limit 1 is reached, cracking in the shotcrete has occurred.
rock mass behaviour differs from the estimated variation in the performed assessment in combination with load variation.
Alarm Limit 2 is set at a level that may indicate that the The Observational Limit is based on the assumption Cracks in the shotcrete will be mapped up to 20m back
be sufficient. In the fractured rock zones the spacing between the rockbolts need to be smaller, so from 2 metres centre to centre they go down to 1.5 metres, in some cases. “We identified some parts that needed more design
work, more support, and more extensive grouting; and those we treated separately,” he adds.
“We had also had some parts where we didn’t have
any rock cover, and in those cases we had choices. Open cut was the simplest and cheapest, but some areas of the Bypass go under an environmentally sensitive area where that was not possible. In those areas we could do some work but we were not allowed to make any permanent changes to the surface. And, it was
April 2025 | 19
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43