search.noResults

search.searching

saml.title
dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
COVER STORY | SWEDEN


While the specific concept developed may be uniquely applicable to the specifics of control rod segmentation at Ågesta, the overall approach which combines standard equipment


and technology to deliver a unique bespoke solution may offer a


useful model for projects elsewhere


Above: Linda Ekstrand, Vattenfall’s project leader for the control rod segmentation at Ågesta


V was mounted on the guide rod head. In several cases the locking mechanism offered stubborn resistance before releasing. In March 2020 the remaining 26 control rods were


lifted, cut and replaced in their original position without additional problems. Nuclide specific activity measurement was done with a CZT-probe on each concrete package. Once all the control rods’ absorber parts were segmented, the remaining parts of the control rods could be segmented using a metal band saw. Here, too, standard equipment could be combined with custom- made equipment to solve the task of sawing, lifting and sorting to different waste fractions. The activity levels of the different neutron-induced material fractions were assessed separately and later combined in the same containers before transport.


The amount of loose activity released from the absorber


during cutting was less than had been prepared for, but the enclosure around the scissors fulfilled its function well and kept the any freed contamination enclosed. All parts of the rods have been transported in the shielded containers to SVAFO’s interim intermediate level waste storage facility in Studsvik. SVAFO has reloaded all


barrels into larger containers which can hold five 80 litre barrels. The control rod dummy unit will be donated to the Technical Museum in Stockholm, along with some other artefacts from Ågesta.


Overall assessment By using a tailor-made arrangement of proven equipment and technology it was possible to develop an innovative technical solution to enable the in-situ segmentation of control rods. This enabled the work to proceed safely in a challenging work space with limited access and constraints on equipment volume and logistical areas. To proceed from the initial design concept to delivery of an optimised functional technical solution, entailed considerable up-front work and adaptations to mitigate risks. This development was driven by Vattenfall in close cooperation with designers and manufacturers. “While the specific concept developed may be uniquely


applicable to the specifics of control rod segmentation at Ågesta, the overall approach which combines standard equipment and technology to deliver a unique bespoke solution may offer a useful model for projects elsewhere,” says Ekstrand. ■


Future D&D and waste management plans The decommissioning programme at Ågesta started in 2020 and is due to be finalised in 2025. Clearance measurements have already been completed for the cooling tower, turbine building, control room and switchgear building, and the cooling tower has been demolished.


Inside the controlled zone, other D&D activities are under way: removal of reactor internals and RPV; removal of other systems; and equipment decontamination which has been ongoing during the whole decommissioning period. The control rod cutting was the third major project to be completed. The next large project will be reactor pressure vessel and internals in situ segmentation.


Preparatory work is under way on site, and first segmentation is planned in early 2022. The total amount of waste generated during decommissioning activities will be about 2000t, of which 1000t is estimated to be radioactive. To date around 650t has been dismantled. Active waste is being sent to AB SVAFO’s interim storage facility at Studsvik, pending disposal.


The aim of the Ågesta D&D project is to leave the decontaminated underground facility structure in place and seal the underground cavern and tunnel. When the work is completed and the facility is cleared and sealed, Vattenfall will return the sealed cavern and the area surrounding it to the City of Stockholm, which owns it. The released site can be used for any purposes. ■


36 | February 2022 | www.neimagazine.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61