feature staircase.”
It too a ull year to finally get the goahead for both the conversion and the extension, but for the Connells it was worth the wait. They started work in January 2019 – just weeks ahead of lockdown. As their contractual work slowed down as a result of the pandemic, Gareth redirected his team to the conversion which was completed in just seven months – even taking into account delays in the delivery of windows and roof slates.
They began by demolishing the cow shed and digging out the barn oor by 00 mm to increase the overall ceiling height. “Local farms took away most of the building materials from the cow shed, so there was very little waste,” said Gareth. More than 200 tons of muck and mud were
removed rom the barn oor which had no footings – before the entire area was sealed with a damp proof membrane and covered with steel mesh encased in 100 mm of concrete. Spies were let in or fiing 00 mm thic steel cage internal retaining walls, which were built inside the stone wall exterior to create a secure inner casing.
A steel skeleton was then built to shore up
the roo while new first oor oists were bolted to the external walls, and timber frames constructed to create the internal walls downstairs. Some of the original roof trusses were retained, supplemented by new sections to run the full length of the barn, before the old corrugated iron roof could be replaced with slate and the supporting steels removed. he house was fitted with waterbased underoor heating and high spec insulation irst and second fies were completed relatively quickly, along with plastering and decoration. he ground oor includes large areas o polished concrete which took a week to complete, but is
54
www.sbhonline.co.uk
Some of the original roof trusses were retained, supplemented by new sections to run the full length of the barn
now one of the Connells’ favourite features in the house.
“The conversion was very straightforward, but it certainly helped to have a ready-made team of tradespeople to ensure everything ran smoothly,” said Gareth, whose background in plumbing came into its own during the build. “Although we didn’t include any eco-features – especially as we wanted to retain the barn’s historic character – we were respectful of its original structure and recycled everything we could.”
This included the building of the extension using materials salvaged from areas of the barn which were dismantled to create space for bi-fold doors and feature windows. The original stone at the front of the property was then cleaned and repointed with lime mortar, and damaged stones replaced with reclaimed ones, to give the old barn walls a new lease of life. All access to the back of the barn – including trafic caused by deliveries and building vans was supported by the Church, who allowed the Connells to use a piece of wasteland that they
sep/oct 2022
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76