FIXTURES & FINISHES
crushed concrete inside of the edge restraints, rake to the desired level in layers of 50 mm, then level and compact using a vibrating plate. The roadstone should be at least 160 mm thick after compaction. We’d recommend passing the vibrating plate over the area at least seven times to ensure it is thoroughly compacted.
SCREEDING
Get the driveway wrong and the whole image of the front of a property becomes unbalanced
position, haunch the back of the units so that the concrete reaches halfway up the rear of the kerb.
SUB-BASE Lay MOT Type 1 Roadstone or Type 1
Once this has been done, apply a layer of slightly damp sharp sand to a depth of 40 mm and compact with the vibrating plate. A second layer of sharp sand to a level of 20 mm should then follow on top of this. Using the string lines, screeding rails and straight edge, this second layer of sharp sand needs to be levelled to the correct falls.
PAVING INSTALLATION
Always begin laying block paving from the bottom of a slope, preferably starting from a right angle or a straight edge. Place the blocks on top of the laying course ensuring blocks are around 10-15 mm above the desired finished level. Continue with your desired pattern while making sure that you are using blocks from between three to five packs at once in order to minimise any colour banding. When all the full blocks have
been laid, you will need to cut a certain amount of blocks to fill the smaller gaps. This can be done by using either a block splitter or a diamond disc saw. A handy tip here is to avoid cutting a block to less than a third of its original size.
FINISHING TOUCHES
Once all of the blocks have been laid, sweep the drive thoroughly to make sure that there is no debris left on the blocks. Then apply kiln dried sand and sweep across the whole of the drive, making sure that this sand falls down between the joints of the blocks.
Having completed this, the drive needs compacting with the vibrating plate. We recommend a neoprene faced or rubber sole plate on vibrating plate compactors to reduce scuffing. You will then need to sweep more kiln dried sand over the drive and compact again. Keep doing this until all of the joints are full of sand. Once this final task has been
completed, the driveway is ready for use. However, make sure all work on surrounding areas that vehicles will pass over is also ready for use to prevent any staining or material transferring to your new driveway as a result.
Lee Dunderdale is product manager at Bradstone
Need help with your wooden fl oor?
For new installations or renovations – speak to your local Bona Certifi ed Contractor!
At Bona we are passionate about wood fl oors. Our range of oils and lacquers have been used worldwide for nearly a century to protect and fi nish beautiful wood surfaces.
ot
To help you prolong the life of your fl oor, we’ve trained a network of wood fl oor specialists in the use of our dust-free sanding system and high performance coatings.
Call us on 01908 525 150 or use the ‘Find your contractor’ tool on our website at
bona.com to fi nd your local wood fl oor specialist.
Bona Limited Tel 01908 525 150
info.uk@
bona.com
bona.com
44
www.sbhonline.co.uk
march/april 2019
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52