SECRETS OF SUCCESS
Chapter two: preparing for demolition
When we heard from first-time self-builders Sarah and Andy Ball in the last issue, they were at a crossroads, unsure if their Derby build would go ahead. Things have changed however, and the demolition notices are in
W
hen we left you last time, we were on tenterhooks. A decision had to be made about number 41. We were living in a house that needs to either be knocked down or have major surgery. After losing two builders we had to decide whether to abandon plans to rebuild and refurbish the existing house instead. There was a third option, although very unlikely, which was to find a project manager to oversee the build.
It was our architect Dan who came up trumps. He was working with a project manager called Paul on a modern house build just two miles from our plot, and better still there was a chance he would be available. We didn’t hesitate. We asked Dan to set up a meeting straight away.
While all this was going on, Andy and I were also working on Plan B. We were
in talks with a local building company who seemed keen to refurbish our house. After two meetings, discussions of plans and a site visit to a property they had completely refurbished, we were hopeful that they would be able to bring in a proposal on budget. Anyway, we met up with project manager Paul and he seemed up for building the house. He charges a flat fee and works with a team of people he trusts.
At the first meeting, he reckoned he could build the house within our budget. He did some calculations based on the house that he’s currently working on. We decided to take it to the next level and get some more accurate figures. Meeting number two went well. The first things he worked on were coming out at the right prices and it looked pretty likely that rest of the
There have been a couple of issues on the later costings – Brexit has hit us, and steel prices are up
costings would follow suit. Paul is now our project manager. He got started on fleshing out the pricing and started the ball rolling on getting the house ready for demolition – including moving the gas and electrics a safe distance away from the action. There have been a couple of issues on the later costings – Brexit has hit us, and steel prices are up. There was
14
www.sbhonline.co.uk
july/august 2017
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68