PROJECT MANAGEMENT


Mahoney said: “We have to pay for that shift anyway: we pay labour rates per shift. Yes, we have to incur a cost with our customers to arrange for alternative transportation for them, but that’s offset by the increased productivity and shorter duration it takes us as an overall programme. From an industry perspective, we’ve looked at the whole cost of doing it, and the advantages and disadvantages, and we feel this is the best way to do it.”


The operator, First Great Western, has been heavily involved in the planning and advised Network Rail on the best time of year to do the works. “They’ve recommended what’s best for their passengers so we’ve co-agreed that as part of the work scope,” Mahoney said.


Explaining the track works themselves, he explained: “Over time, the existing single line has gone from one side to the other or to the middle; generally speaking it’s on the up side as far as Purton, then there are a few positions where it dives into the centre of the formation. In August, we’ll be moving the tracks around that section onto that same side, out of the middle of the formation. Beyond Purton – between Purton and Swindon – it actually crosses over onto the other side of the railway as a rule, but again there are still a few areas where it dives back into the centre of the formation.


“As far as the travelling public are concerned, we’ll still have a single-line railway operating between the two locations: all we’re doing is clearing it out and making sure there’s a space for us to excavate next to it, so we’ll be able to


work from trains on the existing single line.”


After the blockade, the new track will be installed. “We’ve got an aligned commissioning from that day in September when the blockade ends, we then work on a nightly basis, churning through the route, excavating and installing our new track adjacent to the current running line. Passengers will see no impact, other than what they can see out of the window of their train.


“There are single-to-double railway junctions in place at either end at the moment. We’ll be taking both of those out, putting in new crossovers, and will also go back to cut the rails where the track at Purton goes from one side to the other. We’ll install plain line on both of those lines there to make sure there’s that continuity of rail.”


After the signalling renewals team have done their part of the work, the connection will be made at Easter 2014.


Logistical challenges


Although the civils and track works are not especially complex or challenging, some of the logistical issues with the re-doubling are more so.


Mahoney said: “We have a small fl eet of engineering trains and wagons that we essentially need to gain a monopoly on because we’re going to be using them day-in, day-out. We’re going to have two trains per night going in from next month onwards, when we start our track works. In that August blockade, for example, we’ve got 100 engineering train movements. Logistically, that’s a challenge, and the complexity we deal with is more in terms of the volume we’re trying to do. Plain line track renewal is what we do elsewhere on the network on a nightly basis, but the challenge for us is doing it in the same location night after night, and doing it over 12 miles.”


The milestones are also extremely important, and Mahoney said he was


Although fi nal delivery is just inside CP5, it’s a CP4 scheme, Scogings said, but very much a capacity/capability scheme, not a performance one.


Mahoney explained: “This scheme is about improving the capability of the network for future growth and future demand. There are no defi nitive timetable changes associated with this: that’s not in our remit to push forward, though with the infrastructure we’re providing, the train operator will be able to go to the DfT should they wish and propose timetable adjustments and more services.


“One of the key rationales for doing this scheme is the diversionary capability. It allows us a network operator and infrastructure maintainer to deliver all of the Bristol and the electrifi cation works, for the greater good of the network, without as much impact.”


opinion@railtechnologymagazine.com TELL US WHAT YOU THINK


Timeline


· December 2012: Site earthworks started · March 2013 – August 2013: Enabling works for second track installation · 9 August 2013 – 2 September 2013: 23- day blockade to move existing track to its new alignment


· September 2013 – December 2013: Track works to install the new second line · January 2014 – April 2014: Signalling installation and preparatory works ahead of Easter commissioning


· 13 April 2014 – 22 April 2014: New infrastructure commissioned at Easter 2014 (Source: Network Rail)


“acutely aware” that hitting them is vital. “We’re governed by the regulator, we report all our milestones to them, and they track our performance. We’re under no illusions: if we fail to hit milestones, we’ll be held to account, and a lot of people will be asking serious questions.”


rail technology magazine Feb/Mar 13 | 37


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84