This page contains a Flash digital edition of a book.
FOUNDATIONS


FEATURE SPONSOR


ACCESS ALL AREAS


Geosynthetics are at the heart of an innovative access road design enabling lorries delivering turbine sections to reach the site of a new windfarm in south west Scotland.


When it comes on line in Autumn 2016, the Glenchamber Windfarm in Dumfries and Galloway will generate enough electricity to meet the demands of about 20,000 homes in the area.


PROJECT DETAIL


Renewable energy firm RES appointed main contractor Luce Bay Group to build the windfarm, which included widening 4.5km of local roads, plus construction of 5.9km of windfarm tracks and a new 2.8km access road across the peat bog surrounding the site. Construction began in 2015, with the sections of the 11 turbines due to arrive on site a year later.


ACCESS


“The windfarm tracks and access road were a critical part of the project.” says Luce Bay Group Project Manager David McCracken. “It was imperative that we delivered them in time for the arrival of the first turbine sections in February this year, so they had to be economical and fast to build; plus they had to perform immediately.


“Excavating the thick, very soft peat and replacing it with site-won granular material to form a stable road foundation was impractical, as it would have been time-consuming and expensive.” he explained.


WORKING TOGETHER Luce Bay and its geotechnical consultant JNP Group worked with Tensar International to come up with an alternative solution to dig and replace. This comprised of Tensar’s TriAx TX170-GD geocomposite that was laid beneath the granular road base and TriAx TX160 geogrid


incorporated within it, to form a mechanically stabilised layer. DESIGN SPECIFICATION


“The TriAx geogrid interlocks with the granular particles, confining and restraining them from moving laterally. This increased the aggregate’s bearing capacity and delivered roads able to carry the heavy construction loads,” explained Tensar Area Civil Engineer, Drew McCartney.


Drew concluded: “Not only did the design ensure the access roads were ready for the arrival of the first turbine sections, but it will also enable the road to perform throughout the operational life of the windfarm, with minimal maintenance.”


Tensar


Click to view brochure Click to view more info


= Click to view video 72 www.windenergynetwork.co.uk


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82