industrial buildings special report


21


BUILDING PROJECTS


The building is constructed around a 2,000 tonne steel framework


task that saw 38,650 dumper loads of top soil shifted and 16,100 cubic metres of concrete laid down by a local company under the leadership of main contractor Shepherd Construction.


Striking


Essentially, the building is primarily constructed around a 2,000-tonne steel framework clad in fully insulated steel sheet.


The metal roof comprises four gable-profiled roof spans


supported by widely-spaced steel columns with skylights covering 10 per cent of the surface and providing natural daylight to the whole factory floor. It is also clad with photovoltaic panels with a combined generating capability of one megawatt, making a significant contribution to the building’s energy supply. In addition, the building features dimmable LED lights with daylight sensors to minimise power consumption during daytime. Anyone approaching the front elevation of the structure is


faced with the striking facade under the first span, featuring two-tone low-E glass to the front and side and shaded by metal brise soleil to minimise solar heat gain. The offices and staff facilities are located behind this glass area which is internally separated by firewalls from the manufacturing areas. “There’s a cutting edge spatial arrangement for both office


and production areas allowing for future flexibility,” explains Elliott. “Workforce comforts and benefits are also carefully considered and there is strong provision for canteens, showers, locker space and excellent cycle storage space. Next to the offices and staff facilities is the hardcore


Newton Aycliffe has the capacity to run more than one production line at a time


industrial part of the building where trains are actually assembled and rolled out. Studies of various manufacturing scenarios were undertaken, including associated activities such Continued overleaf...


‘Even with the planning green light given, it was obvious that such a large scale manufacturing facility would require a significant amount of essential services and utilities to be provided’


respond online at www.architectsdatafile.co.uk


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68