Parameter


Potential Maintenance Activity


Cable re-burial using jetting


Worst Case Assessed in the Environmental Statement


The coastal process model has assumed the maximum number of cables and cable lengths as shown in 'Additional Cable Laying'. Maximum increases in suspended sediment concentrations and deposition have been modelled assuming a worst case of jetting/vertical injector techniques and cables buried up to 5m depth. The worst case assessment in terms of impacts on ecology is as follows: (i) For export cable, assumes dredging work and jetting along 80% of cable and trenching along inner 20% of cable. For interconnector and inter-array cables, assumes dredging and jetting. In terms of substrate loss, jetting impact width assumed to be up to 5m and trenching impact width assumed to be up to 50m (including spoil area). In terms of maximum sediment disturbance, jetting assumed to be worst case.


Cable repair


See worst case in terms of 'cable re-burial'.


FurtherWorks/ Annex 1 Surveys /Action Needed


Alert the MMO - review availability of current survey data if activities are outside the project envelope. For activities within the project envelope, no further action required (to be reviewed triennially)


Alert the MMO - review availability of current survey data if activities are outside the project envelope. For activities within the project envelope, no further action required (to be reviewed triennially)


Foundations Foundation See worst case in terms of No further action


Outline Operations and Maintenance Monitoring Plan Offshore