INDUSTRYINSIGHT Risking the supply chain


A worrying and increasingly prominent trend is the amount of risk being shouldered by those active in the project logistics supply chain. David Kershaw reports.


Helge Ehlers, a member of the executive board at Hamburg-headquartered freight forwarder Conceptum Logistics. “We are seeing delayed payment terms


O


more and more often, and more rigid credit terms than most of us could even remember. “If [EPCs and project owners] were


more supportive on the payment side, they would get more out of it,” explained Ehlers. “This has become an unhealthy trend.


We are not banks but transport engineers. 90-day payment terms are far too long when jobs have been accomplished long before that. It has put a lot of small and medium-sized enterprises (SMEs) under unnecessary pressure, as they are equally forced to find financing solutions now.” Numerous executives active in the project logistics business echoed this sentiment.


Longer credit lines Justin Archard, corporate director at SAL Heavy Lift, said: Everyone is taking longer to pay. It used to be almost instant, within a few days of shipping. Now, if you are lucky, you get it when you are breaking bulk. There are those that will not pay until 30 or 60 days after you have broken bulk. All of this is just adding further pressure on shipowners.” Forwarders and shipping lines alike are


essentially providing overdraft facilities to their customers. Freight rates are certainly not at a level to merit the increased risks facing SMEs active in the logistics sector. For some, the situation remains


manageable, with borrowing costs still relatively cheap. However, a notable increase


26 January/February 2019


ne of the most visible trends in the project logistics sector has been the change to payment terms: most notably, their increasing duration, according to


in interest rates will put all but the very largest firms offering extended payment terms under immense pressure. We reported in the September/October


2018 edition of HLPFI that there is an increasing trend of what has traditionally been classified as manufacturer or construction risk being incorporated into cargo coverage. This is happening against a backdrop of increasing project logistics activity. In some cases, project cargoes get


shipped with owners and insurers having different ideas of what is covered and what is


excluded. Underwriters have cautioned that incorporating some of what used to be manufacturer or construction risk into cargo coverage must be done with very specific wording. Another long-running trend that


continues to affect those active in the project logistics sector is excess competition, and the continuing battle price. Unfortunately, there appears to be only


one way that players in the market can respond to the risks being pushed upon them. According to Archard: “This situation


will not improve until there is a genuine recovery in the sector. It will not be until a firmer market comes that you have the strength to respond to these demands.” He added that charter rates need to


double if shippers expect to continue receiving the levels of service they have come to expect. “Everybody wants service. But, you cannot maintain a service like this without making some money.” There are some early indications that this


... there are many signs on the horizon predicting that overall logistics costs will increase going forward. – Ivar Myklebust, Höegh Autoliners


situation is starting to change. Ivar Myklebust, ceo of Höegh Autoliners, said: “After a number of years where the benefits of improved productivity have mainly been transferred from suppliers to the customers, there are many signs on the horizon predicting that overall logistics costs will increase going forward. “This is necessary to allow for


re-investment and normal profitability throughout the supply chain,” he explained. HLPFI


www.heavyliftpfi.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150