The provision of all this data identified several requirements along the route to enable the convoy’s safe passage, this included street furniture removal, relocation of signage and lamp posts, pruning of foliage, third party land requirements and certain sections where the placing of track way would be necessary.


The tower sections would move freely along the route but these special measures were essential for safe delivery of the blades. After liaising with several authorities, highways departments and constabularies the route was agreed and adapted to accommodate the convoy, now all that was needed were the turbines themselves.


SHIPPING


Cue the arrival of the ships. Handled by Collett’s Marine Division, two vessels were expected at the Port of Grangemouth, the first arriving from Poland carrying the nine turbine blades, the second from Turkey carrying the nine tower sections.


As the vessels arrived the company was on hand portside ready to begin the discharging of the ships. One by one each of the components were safely lifted from the vessel to an agreed laydown plan portside at their Grangemouth Heavy Lift Storage Facility. Utilising the company’s 110Te straddle carrier and various craneage equipment, each component was strategically positioned to allow for ease of loading in line with the delivery schedule. Here the loads would remain until the stage of construction at Muirhall could facilitate delivery allowing Collett to provide a 'Just in Time' service.


HUBS AND NACELLES – ANOTHER CONSIDERABLE CHALLENGE


The hubs and nacelles for each turbine were located in Germany. This provided yet another logistical challenge requiring expert co-ordination from Collett to ensure an orchestrated arrival of the components necessary for each complete turbine. The company once again rose to the challenge, with expert logistical planning and execution they ensured that deliveries of these integral components fell in line with the agreed schedule.


DELIVERY DETAIL


As the end of November approached the first delivery to site set off. In order to minimise disruption, and due to the size of the cargoes and the route they would be travelling, each convoy consisted of one tower section and one turbine blade.


= Click to view video


Accompanied by Collett’s pilot vehicles and under police escort the convoy made its way along the route, manoeuvring the components through the villages of South Lanarkshire with their expert drivers effortlessly taking the challenging route in their stride.


After crossing splitter islands, employing contraflow manoeuvres and utilising manual steering at key points throughout the route all components arrived safely on site ready for construction.


DELIVERY SCHEDULE


Working on a 6 day a week delivery schedule, and adopting the blade and tower delivery combination, each component safely made the journey from Grangemouth to site, arriving in synchronisation with the construction schedule.


Working closely with the experienced Muirhall wind energy team on both this and the previous phase two extension allowed the company to provide expert logistics throughout.


RISING TO THE CHALLENGE


From coordinating the arrival of components from three separate locations across Europe to the extensive planning and execution of manoeuvring a 63.35m loaded combination, Collett rose to the challenge and are proud to say that they’ve delivered the largest onshore turbine blade in the UK.


Muirhall Windfarm phase 3 extension, also known as Muirhall South is expected to be operational in early 2016 and will offset circa 10,848 tonnes of CO2 per annum whilst supplying up to 5,773 homes with electricity over the 25 year lifetime.


Collett & Sons


Click to view latest news Click to view website


www.windenergynetwork.co.uk


17


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84