Construction News Awards 2012
Project £10m to £50m
WINNER MORGAN SINDALL FOR PADDINGTON STATION SPAN 4 RENEWALS JUDGES’ COMMENT
“This was a once in a lifetime project the whole team should feel proud of, a fantastic scheme that has overcome huge challenges”
Morgan Sindall won the contract to restore the fourth span of Paddington Station’s roof, extending its life by 75 years, while maintaining a live environment at one of London’s busiest stations. This span, added in 1916 to
Isambard Kingdom Brunel’s original three-span design, fell into disrepair in the 1990s. Morgan Sindall’s £42.25 million
restoration project meant work on a Grade I-listed building serving up to 180,000 passengers a day. Six platforms had to be kept operational and watertight. Network Rail also required the
Sponsored by FINALISTS
● ATKINS/MORGAN SINDALL ● BALFOUR BEATTY GROUND ENGINEERING AND MOTT MACDONALD
● GB BUILDING SOLUTIONS ● INTERSERVE CONSTRUCTION ● SHEPHERD CONSTRUCTION ● THOMAS VALE CONSTRUCTION ● VINCI CONSTRUCTION UK
32 | 12 July 2012
contractor to liaise with stakeholders including First Great Western, Westminster City Council and English Heritage. Site workers erected a
temporary works structure consisting of a 5,800 sq m protection deck and 6,000 sq m hanging access scaff old during pre-planned possessions to carry out the construction work safely in non-possession periods. Chutes dispensed materials,
minimising manual handling. An extra level of complexity was added with a 3,000 per cent
change in steel repairs that aff ected all elements of the project, the requirement for which only became apparent after removal of the old roof. Providing more than one plan
for each work area, and reviewing them to achieve the best possible solution, the contractor worked with Network Rail to stay within the original site constraints. A safe plan was proposed to
Network Rail to allow two tower cranes and a mobile crane to be used above a live railway line. Daily co-ordination meetings
allowed the team to look at a plan of the site where diff erent trades were working. The client attended weekly co-ordination meetings. Detailed cost reporting on all
variations was submitted regularly to the client. The fi nal account was settled
before the revised contract completion date, while all major subcontractor fi nal accounts were agreed within three months of the completion date. There were no disputes, strikes or claims on the project.
Judges Phil Akrill, Rebecca Evans, Graham Kean
FOCUS
RICHARD POLLARD PROJECT DIRECTOR
Working on the refurbishment of Span 4 of Paddington Station, there was a responsibility to ensure
the quality of the works did justice to the original structure. This was achieved by drawing
together experience from Morgan Sindall infrastructure and construction projects, using experienced subcontractors and close co-operation with Network Rail and English Heritage. To maintain the programme after
the full extent of the repair work was identified required full co-operation by all trades. Working with Network Rail,
which progressively carried out inspections of the works, minimised final snagging. Upon removing the protection
deck to reveal the final light and airy structure, and to receive compliments from both Network Rail staff and members of the public, it was clear that we had achieved the objective.
www.cnplus.co.uk
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37