This page contains a Flash digital edition of a book.
FESTIVAL: SZIGET 2011


SZIGET 2011


TRADITIONAL HUNGARIAN ISLAND FESTIVAL, SZIGET, IS THE LARGEST OF ITS KIND IN CENTRAL EUROPE. SOME 65,000 PEOPLE ENJOYED THE EVENT ON THE RIVER DANUBE DURING 2011. WITH A TOTAL OF 385,000 VISITORS OVER 10 DAYS, ALMOST 300-STRONG TECHNICAL STAFF ENSURED THE ENTERTAINMENT WENT SMOOTHLY VIA PRECISE TECHNICAL COORDINATION THAT SAW THE OPERATION OF AN IMPRESSIVE SIX LARGE AND 32 SMALLER STAGES. LOCAL REPORTER TAMAS BARDOS WAS THERE...


Technical Production Director, Bela Dudas, is responsible for the coordination of sound, light, stage and power systems over all of Sziget’s stages. Dudas explained that technical planning started in November 2010, however, the vast majority of the organisational work continued into spring 2011. A challenge for Dudas’s crew was that the very same technical staff were also busy working on various other events – also organised by Sziget Co Ltd - including Balaton Sound and Volt Festival. These events continuously took place from the beginning of the summer in Hungary.


A NEW FAÇADE Based on the experiences of previous years, the organisers designed a new facade for the main stage. This was requested for a better appearance, greater security and a more favourable structural solution. The improved security was mainly served by a static structural stage design that also offered strong wind resistance.


68 • TPi NOVEMBER 2011 This new stage construction (with its 120 tonne


metal structure) was capable of holding two 70 sq metre LED walls, each with a total weight of eight tonnes, a 14 tonne loudspeaker system and the 15 tonne lighting rig, which required a six-day build. The power system for the festival’s 38 stages


was completed in just under two weeks by 40 crew, with electricity company, ELMÜ, ensuring that sufficient energy was accessible on site. More than 100 different audio-mixers, 3,500 lamps and almost 700 loudspeakers were set up for the event and five temporary transformers were connected to provide 298W of energy during the festival’s duration. Sziget’s organisers set up a management


centre for the duration of the festival that was continuously in contact with the meteorological office. Based on the unexpected weather warnings, the festival managers made the decision that the advertisement boards had to be removed from the stage structure due to an approaching storm.


Above: The PA was flown by a team of 20 experts who joined forces to build Sziget’s main sound system.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92