Pipeline project
ahead of schedule
Ken Gousseau Canadian portion of the project includes the
Medicine Hat News
construction of about 373 km of new pipeline
and the conversion of about 864 km of existing
Construction of the TransCanada Keystone
TransCanada pipeline from natural gas to crude
pipeline in Oyen is well ahead of schedule,
oil transmission.
company officials say.
“This is an innovative, cost-competitive way to
By mid-March, 202 kilometres of the 3,456 km
accommodate the expected growth in Canadian
first phase of the oil pipeline will be completed,
oil production during the next decade,” says
leaving 71 km for summer 2009 construction in
TransCanada spokesman Terry Cunha. “The
Alberta. The pipeline is scheduled for completion
pipeline will also serve the interests of the United
by the fourth quarter of 2009.
States by providing a secure and reliable supply
The town of Oyen, located about 145 km north
of Canadian oil to meet the growing demand in
of Medicine Hat, is the location chosen as
the U.S. “
the headquarters for the construction team
Keystone has secured commitments for 910,000
tasked with completing the 273 km of Alberta
barrels per day over an average term of 18 years.
construction for the Keystone pipeline project.
This represents about 83 per cent of the system’s
Photo Courtesy Trans Canada
Ledcor Pipeline Ltd. is the principle contractor
capacity. When completed, the pipeline will
for the project.
transport about 1.1 million barrels of oil per
In Alberta, the pipeline construction crew will
day and result in a total capital investment of
peak at about 700 workers as well as several
approximately $12 billion U.S.
hundred people constructing the Hardisty
About 40 Alberta communities will benefit from
terminal and the pumping stations. The entire
local spending and tax revenues generated by
project will peak at approximately 7,000 workers
Keystone, TransCanada says. Additional tax
in the summer of 2009.
revenue will be generated due to new facilities
The pipeline will stretch from Hardisty, Alta, to
being installed, such as pump stations.
Cushing, Oklahoma and Patoka, Illinois. The
Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71