Sno Organisation Project Title / Details Location Budget* Contacts Sector
60 Era Infra The company’s construction & contracts Mauda 223.00 Mandeepa Ahluwalia, Power
Engineering division has got a contract from NTPC Maharashtra AGM-Comunications, B-124, Sector
Ltd for Mauda Super Thermal Power Project, - 3, Noida - 201301. T: 0120-4145000,
Mauda (2X500 MW), Maharashtra. The 4037000, M: 09910446604,
project involves the Main Plant and mandeepa.a@eragroup,
Offsite Civil Works Package. Era Infra (H S Bharana, CMD)
will complete the project work within 43
calendar months from the issue of letter
of award.
61 Sadbhav NHAI has awarded the contract for 4/6 Dhule 1415.00 Parul Shah, Sr. Business Develop- Roads/
Engineering laning of MP/Maharashtra border to Maharashtra ment Offi cer, Sadbhav House Off Law Highways
Ltd HCC- Laing - Sadbhav Consortium. Garden Police Chowki, Ellisbridge,
The scope includes design, engineer- Ahmedabad-380006. Gujarat.
ing, fi nance, procurement, construction, T: 079-26463384, F: 26400210,
operation and maintenance of 4/6 laning
parul.shah@sadbhaveng.com
of MP/ Maharashtra Border- Dhule (Vishnubhai M Patel)
section of NH- 3 from km 168.500 to
km 265.000 in the State of Maharash-
tra under NHDP Phase IIIA on BOT
(Toll) basis. The work will start in 6 to 8
months. The Concession Period of the
project is 18 years inclusive of construc-
tion period of 30 months.
62 IVRCL The company has got contract from Bangalore 168.28 1) ME Gururaj, Dy Mgr, No.438, Transporta-
Infrastructure Bangalore Metro Rail for construction of Karnataka 18th Main, Ist fl oor, 6th Block, tion
and Projects buildings and industrial structures along Koramangala, Bangalore - 560095.
Ltd with building elevated metro stations at T: 080 - 25634966, 25500030, M:
CMH Road, Byappanahalli, Old Madras 09986193162, ivrclbro@ivrclinfra.
Road and Ulsoor for the metro rail project com. 2) Sudhakar Nayak, Manager
phase I. The project is expected to com- Protocol, 3rd Floor, BMTC Complex,
plete in 22 months. K.H.Road, Shanthinagar, Bangalore-
560027. T: 080-22969300,301,
F: 22969222,
bmrcl@dataone.in,
M: 09448287977.
Joint Venture (Sno. 63)
63 Karnataka Agreement signed for setting up Joint Raichur .. KPCL: Thirumalleswar Bhatt, Super- Power
Power Venture company to Build, Own and Karnataka intendent Engineer, Shakti Bhavan,
Corporation Operate the 2x800 MW Coal Based 82, Race Course Road, Bangalore
Ltd / BHEL Supercritical Power Plant at Yerama- - 560001. T: 080-22258431, 22256568,
rus, Raichur, Karnataka, & 1x800 MW F: 22252144, M: 09449039899.
Coal Based Superitical Power Plant at
Edlapur, Raichur, Karnataka.
Project Update/Commissioned Project (Sno. 64 to 72)
64 Sagar The company has successfully com- Andhra .. K Ganesh, GM-Projects, 8-2-472/B/2, Cement
Cements pleted the expansion of its capacity from Pradesh Road No.1, Banjara Hills, Hyderabad-
Ltd 0.60 million tons to 2.35 million tons at its 500034. Andhra Pradesh. T: 040-
plant in Mattampally in Nalgonda District, 23351571-73, F: 23356573. ganeshk@
Andhra Pradesh.
sagarcement.com ( S Veera Reddy, MD)
65 Subburaj The company has recently commis- Tirunelveli 200.00 Balasubramaniam, DGM-Market- Paper
Papers Pvt sioned a 300 tonne-a-day recycled Tamil Nadu ing, Madurai Road, Shankar Nagar,
Ltd paper plant located at Ambasamudram, Tirunelveli - 627357, Tamilnadu.
about 25 km from Tirunelveli. The unit T: 04634-275201, 0462 -2300296,
is now producing over 60-70 tonnes of 2300647, F: 2300497,
printing and writing paper daily. 6-MW
papers@subburaj.com
coal-based captive power plant is also
commissioned.
66 Lanco The subsidiary company, Vamshi Hydro Himachal 30.00 Amit.Goyal, Project Engineer, Vamshi Power
Infratech Ltd Energies Pvt Ltd has successfully Pradesh Hydro Energies Pvt Ltd, Sharma Niwas
Commissioned IKU-II (5 MW) Small Shyam Nagar Dharamshala-176215,
Hydro Project in Dharmshala, Himachal Himachal Pradesh. T: 0124-4741446,
Pradesh, and has commenced Commer- F: 229096,
cial Operations with effect from January
amit.goyal@lancogroup.com.
19, 2009.
*Figures are approximate (Rs. Crore)
Project Reporter • 13 • March 1, 2009
Project Reporter.indd Sec1:13 26/02/2009 12:14:34 PM
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24