INDUSTRIAL FLOORING


How to get the best results with


floor screed The way to achieve best results is to consider the final performance requirement based on the floorzone. Most flooring is designed from the concrete upwards and final floor finishes are generally left as a later decision. Quite often this leads to failure as potentially the requirement in the British Standards of each floor finish are different, leaving joints in the wrong place, no intermediate movement joints, change of usage category, drying time suitability and compatibility. It is therefore best practice to consider designing from


the top down, being the final floor finish, back to the concrete substrate.


Our recommendation would be to collate all the requirements from the floorzone and consider all options with their particular design requirements and associated standards. Once this information is complete, the design and markup of drawings can be produced. It’s always a good idea to have this information shared with all relevant parties in order to achieve best results.


Once all the above has been completed, the floor screeding installation process can begin as follows:


• Check the area is free of debris, materials and trades.


• Check the area is watertight.


• Check the correct depth of screed can be achieved by measuring down from the datum level.


• Ensure the correct depths, movement joints, expansion perimeter strips, acoustic / thermal layers, membranes are in place.


• Check the specification of the screed mix design.


• Ensure the mixer is a forced action type such as a pan mixer or screed pump.


• Disperse the Fibres into the water bucket used for each mix and agitate for two minutes.


• The mix should be of a plastic consistency.


• Continue to complete the screeded area.


• The following day, protection can be installed. Consider the expected traffic and beef up the protection if necessary; A very important consideration for high volumes of traffic.


• Protection to remain in place until final floor finishes are installed.


www.screedscientist.com


twitter.com/TomoFlooring


31


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66